UCS Cutover-Related Activities and Deliverables [III, Voyager, WMS] UCS Cutover-Related Activities and Deliverables [III, Voyager, WMS]
-
Submit Scheduled jobs list to EXL [III, Voyager, WMS] Note Due: Jun 14, 2021
-
All data extracts due to EXL by EOD / 5pm PT [III, Voyager, WMS] Due: Jun 18, 2021
-
360/Intota reports due to EXL by EOD / 5pm PT [Voyager, CDL] Due: Jun 18, 2021
-
P2E file due to EXL by EOD / 5pm PT [III, Voyager, WMS] Due: Jun 18, 2021
-
Migration form due to EXL by EOD / 5pm PT [III, Voyager, WMS] Due: Jun 18, 2021
-
Field mapping due to EXL by EOD / 5pm PT [only III and WMS] Due: Jun 18, 2021
-
Delivered files list due to EXL by EOD / 5pm PT [III, Voyager, WMS] Due: Jun 18, 2021
-
Contact all electronic data suppliers with a request to use the Alma Link Resolver [Campuses and timing TBD] Note
-
Alma NA07 NZ lock-out by EOD / 5pm PT [ All campuses] Due: Jul 5, 2021
-
[Optional] Download Alma Offline Circulation Tool [III, Voyager, WMS] Due: Jul 23, 2021
-
Data review and testing on NA07 [III, Voyager, WMS] From: Jul 23, 2021 - Jul 26, 2021
-
Immediately report to EXL any migration issues found during your testing via your Cutover case [III, WMS, Voyager] From: Jul 23, 2021 - Jul 26, 2021
-
Provide written data acceptance for Alma via your Cutover case [III, Voyager, WMS] Note Due: Jul 26, 2021
-
Provide written acceptance of your Primo VE environment via your Cutover case [III, Voyager, WMS] Note Due: Jul 26, 2021
-
Provide EXL your Cutover Fulfillment data by EOD / 5pm PT [III, Voyager, WMS] Due: Jul 26, 2021
-
Review your Fulfillment Cutover data migration [III, Voyager, WMS] Due: Jul 27, 2021
-
Provide written data acceptance for your Fulfillment data via your Cutover case [III, Voyager, WMS] Note Due: Jul 26, 2021
-
Notify EXL you are ready for Go Live - EXL will run Go Live jobs [III, Voyager, WMS] Due: Jul 27, 2021
-
Upload Alma offline circ files to Alma - note: can also be done post Go Live [III, Voyager, WMS] Due: Jul 27, 2021