UCS Pre-Cutover Activities [III, Voyager, WMS]
UCS Pre-Cutover Activities [III, Voyager, WMS]
Cutover cases have been set up with the same primary contact as your Test Load cases. Please inform EXL if there are any any changes needed - via your Cutover case. [III, Voyager, WMS]
Due: Jun 11, 2021
If you are migrating ACQ, inform EXL if you plan to perform FY rollover in your ILS prior to Cutover - via your Cutover case [UCB, UCLA, UCSD, UCSF]
Due: Jun 11, 2021
Inform EXL if you plan to opt-out of ProQuest Activations at Cutover via your Cutover case [III, Voyager, WMS]
Due: Jun 11, 2021
Confirm that you can access your MFT shares or report issues via your Cutover Case [III, Voyager, WMS]
Due: Jun 11, 2021
Inform EXL if you plan to use a custom domain for Primo VE and the Primo Service page via your Cutover case [III, Voyager, WMS]
Due: Jun 11, 2021
Download latest auto-extract kit [Voyager only]
Due: Jun 11, 2021
Download latest version of file validation tool [III only]
Due: Jun 11, 2021
Download the Non-ExLibris to Alma Data Validation tool [WMS only]
Due: Jun 11, 2021
Review your *Test Load* case notes for needed changes to data and/or forms or for details about expected fixes at Cutover [III, Voyager, WMS]
Due: Jun 11, 2021
Ensure all libraries, locations and vendors in current ILS are reflected in Alma with the same codes [III, Voyager, WMS]
Due: Jun 11, 2021
Technical Services freeze by EOD / 5pm PT or PRIOR based on the date you need to start extracting data [III, Voyager, WMS]
Due: Jun 15, 2021
Freeze SFX by EOD / 5pm PT [CDL]
Due: Jun 25, 2021
NA07 lock-out by EOD / 5pm PT [III, Voyager, WMS]
Due: Jun 25, 2021